In January 2019, SEESARI adopted a Strategic Master Plan. Among its several strategic pillars, the High-Speed Rail was highlighted.
The high-speed lines have the following parameters:
- Double-track rail for speeds of 200 km/h and higher (dependent on studies)
- ETCS L2
- GSM-R
- Mixed terrain railway (hilly-mountain-flatland)
- Railway for mixed traffic
The indicative SEE HSR sections and their lengths are:
- Vienna – Ljubljana ~ 430 km (Vienna-Klagenfurt/Graz: in construction or already planned) => new line Villach – Ljubljana: 100 km);
- Ljubljana – Zagreb ~ 140 km;
- Zagreb – Beograd ~ 400 km;
- Belgrade – Budapest ~ 380 km (in construction or already planned);
- Budapest – Bratislava ~ 200 km;
- Bratislava – Vienna ~ 65 km (planned);
SEESARI Task Force for SEE HSR will be established in 2024. For more information please contact peter.verlic@seesari.org.